Published on
February 26, 2026

Utility-Scale Solar Project Development Stages: The Complete Timeline from Site Selection to COD

Developing a utility-scale solar project is a complex, multi-year process that requires careful planning, technical expertise, and coordination across multiple stakeholders. From identifying a suitable site to achieving Commercial Operation Date (COD), most utility-scale solar power projects follow a structured development process that typically spans between 24–48 months, depending on project size, location, permitting requirements, and grid connection constraints.
7
 min read
Author
Brian Raboin
Brian Raboin
A power and renewable energy photo collage featuring solar panels, windmills, and nature shots.

Unlike smaller solar installations, utility-scale solar project development involves significant capital investment, regulatory approvals, environmental permitting, interconnection agreements with utility companies, and extensive engineering and construction work. Each stage of the project lifecycle carries distinct risks and dependencies, and delays in early phases can ripple through the entire timeline.

In this guide, we will walk through the solar project development stages, explaining what happens at each phase, typical timelines, common challenges, and critical path items. We also highlight where upstream design and optimization platforms, such as PVFARM, play a key role during feasibility, layout, and engineering stages - helping teams reduce risk, improve financial viability, and move toward successful implementation with greater confidence.

PVFARM was named a 2025 Best-in-Show winner by Solar Power World in the large-scale category, recognizing the platform’s ability to deliver prospecting-speed iteration with engineering-grade detail for utility-scale solar design.

Understanding the Solar Project Development Process

Utility-scale solar project development follows a structured but highly iterative process. While individual projects vary, most follow seven core stages, many of which overlap to compress timelines and manage risk. Typical total timeline varies between 24–48 months, depending on permitting complexity, interconnection queue position, and project size.

Stage

Typical Duration

Site Selection and Acquisition

3–6 months

Feasibility and Pre-Development

6–12 months

Permitting and Approvals

6–18 months

Interconnection and Grid Studies

12–24 months

Engineering and Design

6–9 months

Financing and Contracting

3–6 months

Construction and Commissioning

6–12 months

Key Success Factors

Successful renewable energy projects share several common characteristics:

  • Early engagement with utility companies, regulators, and communities
  • Parallel processing of development stages where possible
  • An experienced development and engineering team
  • Adequate contingency in budget and schedule
  • Proactive risk management
  • Flexibility to adapt to regulatory and market changes
  • Early access to engineering-grade design intelligence, using upstream utility-scale solar design software such as PVFARM, which enables teams to iterate layouts 10–20× faster while maintaining buildable accuracy.

Common Delays and Challenges

Some of the most frequent causes of delay include:

  • Interconnection queue backlogs (often 12–24+ months)
  • Environmental permitting reviews
  • Community opposition or zoning challenges
  • Supply-chain disruptions for major equipment
  • Financing delays tied to market conditions

Critical Path Items

The longest-duration activities typically define the critical path:

  • Grid interconnection studies and agreements
  • Environmental and land-use permits
  • Financing commitment prior to construction

Stage 1: Site Selection and Acquisition (3–6 Months)

Site selection is the foundation of the entire solar project development process. Choosing the wrong site can undermine economic viability before engineering begins.

Site Screening and Identification

Key screening criteria include:

  • Solar Resource: Typically ≥4.5–5.0 kWh/m²/day
  • Land Requirements:
    • 5–8 acres/MW (fixed-tilt)
    • 6–10 acres/MW (single-axis trackers)
  • Proximity to Transmission: Ideally within 5 miles
  • Terrain: Gentle slopes (<5–8% preferred)
  • Environmental Constraints: Minimal wetlands or protected habitats

Preliminary Site Assessment

Early desktop analysis includes:

  • GIS mapping of land use and zoning
  • Environmental screening
  • Transmission and electrical infrastructure review
  • Preliminary layout feasibility

A site visit validates access, visibility, and potential construction challenges.

Land Acquisition Strategy

Developers typically secure land via:

  • Long-term lease (20–30 years)
  • Option to lease during development
  • Direct purchase (less common due to capital cost)

Deliverables include a site screening report, preliminary pro forma, and executed land control agreement.

Stage 2: Feasibility and Pre-Development (6–12 Months)

This stage determines whether a proposed project can move forward.

Detailed Site Assessment

Key studies include:

  • Topographic surveys (1–2 ft contours)
  • Geotechnical investigations
  • Environmental assessments (wetlands, wildlife, cultural resources)
  • Solar resource validation and shading analysis

Preliminary Design and Layout

Conceptual system design includes:

  • Solar array configuration
  • Mounting type (fixed-tilt vs tracker)
  • Preliminary electrical infrastructure
  • Access roads and site preparation

Financial Feasibility

Developers build a financial model to assess:

  • Total project cost
  • Energy production and revenue
  • Financial viability (IRR, NPV, LCOE)
  • Sensitivity to cost and price assumptions

Upstream utility-scale design platforms such as PVFARM integrate layout, terrain, energy yield, and cost assumptions, allowing teams to rapidly compare design scenarios and assess early financial feasibility, and evaluate whether projected energy profiles can support Power Purchase Agreement (PPA) pricing before committing to detailed engineering or financing.

Stage 3: Permitting and Approvals (6–18 Months)

Permitting is often the most uncertain phase in utility-scale solar project development.

Zoning and Land-Use Permits

Projects must secure:

  • Zoning approvals or variances
  • Conditional Use Permits (CUPs)
  • Site plan approvals

Environmental Permits

Depending on jurisdiction, permits may include:

  • Wetlands and stormwater permits
  • Endangered species reviews
  • NEPA analysis (if federal involvement)

Utility and Grid Approvals

This includes executing interconnection agreements and coordinating construction requirements with utility companies.

Stage 4: Interconnection and Grid Studies (12–24 Months)

Interconnection is typically the longest-duration process.

Interconnection Studies

Utilities require:

  • Feasibility study
  • System impact study
  • Facilities study

Costs for network upgrades can range from $50–500/kW, depending on grid conditions.

Stage 5: Engineering and Design (6–9 Months)

This phase transforms concept into buildable reality.

Detailed Engineering

Engineers design:

  • Civil works (grading, drainage, roads)
  • Structural systems (racking, foundations)
  • Electrical infrastructure (DC/AC systems, substations)

During the design phase, PVFARM supports layout optimization, grading analysis, electrical topology, and energy yield validation, allowing engineers to evaluate trade-offs early before construction drawings are finalized. This is one reason PVFARM has been recognized by Solar Power World as a 2025 Best-in-Show winner for large-scale solar software.

Energy Yield Validation

Bankable models (e.g., PVsyst) are used to produce final P50/P90 estimates.

Stage 6: Financing and Contracting (3–6 Months)

Once permits and design mature, projects move to financial close.

Financing Structure

Typical structure:

  • 60–80% debt
  • 20–40% equity (including tax equity where applicable)

Contracting

Developers execute:

  • EPC contracts
  • Equipment procurement agreements
  • O&M (Operations & Maintenance) contracts

Stage 7: Construction and Commissioning (6–12 Months)

With permits in place and contracts executed, the project enters the construction phase, translating engineering designs into physical infrastructure on site.

Construction Phase

Key activities include:

  • Site preparation and earthwork
  • Racking system installation
  • Solar panel installation
  • Electrical infrastructure and grid connection

Commissioning and COD

System performance testing verifies:

  • Energy production
  • Electrical safety
  • Grid compliance

Commercial Operation Date (COD) marks the start of revenue generation.

Post-COD: Operations and Asset Management

After COD, focus shifts to:

  • Ongoing maintenance
  • System performance monitoring
  • Renewable energy certificates (RECs)
  • Financial reporting and asset optimization

From Site Selection to COD

Utility-scale solar project development is a long, complex process that demands careful planning, experienced teams, and early risk reduction. While construction and commissioning often receive the most attention, many of the most impactful decisions occur during site selection, feasibility, and design.

Upstream design and optimization platforms such as PVFARM help solar project developers, engineers, manufacturers, EPC contractors evaluate site conditions, system design, and energy production early - supporting stronger financial viability and smoother downstream execution.

With the right tools and a structured development process, utility-scale solar projects can move from concept to COD more efficiently - delivering clean energy, reliable energy production, and long-term value.

Want to See How PVFARM Supports Early-Stage Solar Development?

Explore how PVFARM helps teams optimize layout, design, and energy modeling during feasibility and engineering stages.

Request a demo or contact our team to learn more.

Share this

Table of contents